An approved process is a promise. When the customer signed off your parts, they approved a specific design, made from a specific material, on specific equipment, in a specific place, checked in a specific way. Every one of those things will change during the life of the part. Tools wear out. A supplier closes. A cheaper resin appears. The line moves to make room for a new programme. An engineer finds a better weld schedule.
None of that is a problem. Uncontrolled, any of it is. Many serious quality escapes in manufacturing trace back to a change somebody made with good intentions and without telling anyone: the part was fine yesterday, something changed, and nobody connected the two until the customer did.
Change management is not paperwork that slows improvement down. It is how you make sure that the process the customer approved and the process running today are still the same process, and that when they stop being the same, it was a decision.
This guide covers what counts as a change, who needs to know, the steps from request to cut-in, and what the standards expect. It uses the pump mounting bracket from the earlier articles in this series, and it follows the guide to how a new part is launched through gates, because a change is a small launch.
Five kinds of change
Most procedures cover the first kind well and the rest badly.
- Customer-initiated design changes. A new drawing level, a revised specification. These arrive with paperwork, so they are the best controlled. The risk is on your side: implementing on the wrong date, or mixing old and new stock.
- Your own product or process changes. A new material grade, a changed process parameter, a different inspection method, new or refurbished tooling, a moved line. These are the ones the customer's rules are written for.
- Sub-supplier changes. Your supplier changes its raw material source, its plating subcontractor or its site. You own this change in the customer's eyes, whether or not you were told.
- Unplanned change points. A relief operator on a critical station, a restart after a breakdown, the first parts after a tool repair. Nothing was redesigned, but the conditions the process was validated under have shifted. Japanese manufacturers manage these as "change points", sorted by the 4Ms: man, machine, material, method.
- Temporary changes. A back-up gauge while the main one is being repaired, manual inspection while a vision system is down, a deviation on one batch of material. They are the most dangerous kind, because they are meant to end and often do not.
The question most plants get wrong
The hard part of change management is not approving changes. It is recognising them. Nobody ignores an engineering change note. The changes that escape are the ones that never looked like changes to the person making them.
A maintenance technician replaces a failed weld controller with a newer model. A toolroom "refurbishes" a die and takes the chance to open up a radius. Purchasing moves to a second steel source at the same specification. Production moves a cell twenty metres to free up floor space. Each person did their job well. Each one changed something the customer approved.
The defence is a short written definition that everybody can apply without an engineer in the room. A workable one: a change is anything that alters what the part is made from, what it is made on, how it is made, where it is made, who supplies it, or how it is checked, compared with what was last approved. Then put that question where changes are born: on the maintenance job card, the tooling repair order, the purchasing source-change form and the layout change request. One tick box, "does this alter the approved process?", with a name next to it, catches more than any procedure in the quality manual.
Who has to be told, and who has to approve
There are three possible answers for any change, and the difference between them matters.
- Internal only. You assess it, approve it and record it. The customer does not need to be involved.
- Notify the customer. You tell the customer before the change, and the customer decides whether it wants a new approval.
- Customer approval required. Nothing changes until you have the approval in writing.
Which answer applies depends on the customer's rulebook. In the AIAG method, the PPAP manual lists the situations that require notification, and the customer then decides whether to ask for a re-submission. In the German method, VDA Volume 2 has used a trigger matrix for the same purpose. The draft of its 2026 revision replaced the matrix with a short decision flow of knock-out questions, and it carried one rule worth adopting whatever your customer uses: if the honest answer to a question is "maybe" or "not sure", treat it as a yes. Individual vehicle manufacturers add their own routes on top. Ford, for example, has a formal request that a supplier must have approved before making any change it initiates, and Japanese manufacturers expect change point notifications in advance.
Two rules hold everywhere and are worth putting on the wall.
When you are not sure, ask. A question to the customer costs an email. An unapproved change found at an audit costs the relationship.
Approval comes before implementation, never after. IATF 16949 is direct about this: where the customer requires it, you notify them of planned changes and obtain documented approval before you implement. "We told them afterwards" is a nonconformity even if the change was an improvement.
The nine steps, from request to cut-in
- Raise the request. One form, one number. What is changing, why, which parts are affected, and the earliest and latest date it could happen. Many companies call this the engineering change request.
- Classify it. Which of the five kinds is it? Product or process? Permanent or temporary? This decides who must be in the room.
- Assess the impact with a cross-functional team. Quality, manufacturing, engineering, purchasing, logistics and, where it matters, safety. Ask what the change does to fit, form and function, to special characteristics, capability, capacity, tooling and gauges, packaging, service parts, cost and timing. For design changes, IATF's design change clause names the effects to evaluate.
- Decide on customer involvement. Internal, notify, or approval. Write down the decision and who made it. If the answer is notify or approval, the clock for the customer's reply starts here, so start early.
- Update the risk documents first. Process flow, PFMEA and control plan before the change is made, because the point of the exercise is to find the new failure modes before the parts do. Work instructions and inspection instructions follow from them.
- Validate. A trial run under production conditions, with measurement results and, where a characteristic is affected, a capability study. If the gauge or the method changed, repeat the relevant measurement study.
- Get the approvals in writing. Internal sign-off, and the customer's where required. This is the engineering change order: the authority to implement.
- Cut in under control. Fix the break point: the date, shift, batch or serial number from which parts are made the new way. Decide what happens to old stock, work in progress and parts in transit. Mark the first shipments if the customer asks for it. Train the operators before the first part, not after.
- Verify and close. Check the first production lots against the new requirement, confirm that every affected document is at the new level on the shop floor and not only in the system, tell everyone who needs to know that it has happened, and record what was learned.
Back to the bracket. Purchasing finds a second steel coil supplier at the same grade, with a better price and shorter lead time. Same specification, so it does not look like a change. The definition above says otherwise: who supplies it has changed. The team assesses it and finds two things the specification does not show. The new coil is at the top of the thickness tolerance where the old one ran in the middle, which affects the bend at the press (OP10), and its surface oil is different, which affects weld quality at OP20. The customer's rules list a change of material source as notifiable, so the customer is told and asks for a new submission. The trial run shows the bend angle has shifted and the press tool needs a shim adjustment. The thickness check at receiving (OP00) gets a tighter reaction limit in the control plan, the first three coils are run with extra weld tests, and the break point is recorded by coil number. Without the process, the plant would have discovered both effects in production, on parts already shipped.
Temporary changes need an end date
A temporary change is a controlled departure from the approved process for a limited time. IATF 16949 has a specific requirement for one common case, the temporary change of process controls, and its logic works for any temporary change.
- Decide in advance which back-up methods are acceptable for each control, so the choice is not made at two in the morning.
- Approve the switch internally before it is used, and get the customer's approval first where they require it.
- Set an expiry: a date or a quantity. A temporary change with no end date is a permanent change that nobody approved.
- Review it every day it is running, with someone senior enough to ask why it is still there.
- Keep the parts made under it traceable, so they can be found if the back-up method turns out to be weaker.
- When the normal control returns, verify it before trusting it again.
What the standards expect
ISO 9001 asks for changes to be handled in three places: changes to the management system are planned, design changes are identified, reviewed and controlled, and changes to production are reviewed and controlled with a record of who authorised them and what was done.
IATF 16949 adds detail. There must be a documented process for controlling and reacting to changes, covering changes caused by you, by the customer and by your suppliers. The effects are assessed, the change is verified and validated before implementation, and the risk analysis is on record. A production trial run is expected for process changes. And the customer is notified, and approves, where their requirements say so.
An auditor testing this will not start with your procedure. They will pick a change from an unexpected place, usually the maintenance log, the tooling history or the supplier list, and ask to see its assessment. Then they will pick a recent engineering change and check whether the PFMEA, control plan and work instruction on the line all carry it.
Seven ways change control fails
- The change was never recognised. Covered above. It is the most common failure by a distance.
- The paperwork changed and the floor did not. The new work instruction is in the system. The old one is still laminated at the station.
- The part changed and the risk documents did not. The PFMEA and control plan still describe last year's process.
- No break point. When a problem appears, nobody can say which parts were made before the change and which after, so everything is suspect.
- Sub-supplier changes arrive after the fact. Your purchase terms did not require notice, so you did not get any.
- The temporary change that stayed. The back-up method has been running for four months and has become the method.
- Approval by silence. The customer was notified, did not reply, and the change went ahead. Unless the customer's rules say silence is consent, it is not.
Start this week
Pull the last three months of maintenance records, tooling repairs and purchasing source changes. For each entry, ask the definition question: did this alter what the part is made from, made on, how, where, by whom, or how it is checked? Count how many of those went through your change process. The gap between the two numbers is your real exposure, and it is usually larger than anyone expects.
Then pick one recent engineering change and follow it to the line. Is the control plan at the new level? The work instruction? Can somebody tell you the break point?
The free Change Request and Impact Assessment form below puts the request, the impact questions, the customer-notification decision and the cut-in record on one document, so that the questions are asked in the same order every time.
Frequently asked questions
What is the difference between an ECR, an ECO and an ECN? A request asks whether a change should be made. An order authorises it. A notice tells everyone it has been made. Small companies often combine all three in one form, which is fine as long as the three decisions are still visible.
Do like-for-like replacements count as changes? A true like-for-like, the same model of the same part, does not alter the approved process, though restart checks still apply. A newer model, a different make or an "equivalent" is a change until an assessment says otherwise.
Does the customer need to approve every process change? No. The customer's requirements define which changes need notification or approval. Everything else you control internally, with the same assessment and record.
How long does customer approval take? It varies by customer and by the size of the change, from days to months. Plan for it at step 4, not at step 8.
What about software? If the product contains software, its version is part of the design record, and a new version is a design change. IATF asks for the software revision to be recorded with the change.
We are ISO 9001 only. Is all this required? The nine steps are a method, not a requirement. What ISO 9001 requires is that changes are reviewed and controlled and that you keep a record of the review, the authoriser and any actions. The method is a reliable way to meet that.
Who should own the change process? One named person, usually in engineering or quality, owns the process and the register. The assessment itself must be cross-functional. A change approved by one department is an opinion.
Is anything about to change in the standards? VDA Volume 2 was revised in 2026 with a risk-based approach to approvals and changes. The IATF has named launch and change management as a priority for the next edition of IATF 16949, planned for mid-2027. Neither removes anything described here.