APQP explained: the five phases, the gates between them, and how the VDA maturity levels describe the same launch

26 November 2026

Every new automotive part is launched the same way, whatever the customer calls it. Somebody wins a quote. A team is named. A design is frozen, a process is planned, tools are cut, trial parts are made, a package of evidence is submitted, the customer approves it, and production starts. Advanced Product Quality Planning, APQP, is the name the North American industry gave to doing those things in a fixed order with fixed checkpoints, so that problems are found on paper in month three and not on the line in month eighteen.

Most suppliers know APQP as a list of documents. That is the least useful way to see it. The documents are outputs. APQP itself is a set of decisions, each made at a gate, and each one answering a single question: do we know enough to spend the next block of money?

A gate is not a meeting where the project is presented. It is the point where somebody with authority decides, on evidence, that the risk left in the project is small enough to commit the next stage of cost.

This guide walks through the five phases, the question behind each gate, what the 2024 edition changed, and how the German maturity-level method describes the same launch in different words. It uses the pump mounting bracket from the earlier articles in this series as the running example.

Where APQP sits, and which standard asks for it

ISO 9001 asks for planned and controlled design and development in clause 8.3. IATF 16949 goes further in its supplemental planning requirements: a cross-functional team, project management, and risk analysis that covers the manufacturing process and not only the product. It also asks for measurements at defined stages of the project, reported to top management. That last requirement is what turns gates from a good habit into something an auditor will ask to see.

Neither standard tells you how to do it. APQP is the how, published by AIAG as a reference manual. The current edition is the 3rd, published in March 2024, which replaced the 2008 edition. GM and Stellantis required it from September 2024 and Ford from the end of that year. If your customer-specific requirements still name the 2nd edition, check the customer's current requirement, not your procedure.

If you are certified to ISO 9001 only, nothing obliges you to use APQP. The logic still applies to any product you launch, and it is a tidy way to show an auditor that clause 8.3 planning is real.

The five phases, and the question behind each gate

Phase 1: plan and define the programme. The team turns the customer's request into a feasible plan: requirements, volumes, dates, targets for quality and capability, a first list of special characteristics, and an honest statement of whether the plant can do it. The gate question is "Do we understand what we have promised, and can we deliver it?" For the bracket, this is where somebody notices that the quoted volume needs a second weld cell by month fourteen, before the price is fixed, and not after.

Phase 2: product design and development. For a supplier that designs its own product, this is the design FMEA, design verification, drawings and specifications, and prototype builds. For a build-to-print supplier, the customer does most of it, but you still own one job here: reading the drawing as a manufacturer and saying, in writing, what you cannot hold. The gate question is "Is the design stable enough to design a process around?"

Phase 3: process design and development. The process is designed on paper before it is built in steel: the process flow, the PFMEA and the pre-launch control plan, plus layout, tooling, gauges, packaging, work instructions and the plan for measurement system studies. The gate question is "Have we planned a process that can meet every requirement, and do we know its weak points?" This is the gate that matters most and is skipped most often, because the tooling order is already late and nothing physical exists to argue about.

Phase 4: product and process validation. Now the real process runs: production tools, production operators, production gauges, at the quoted rate. The significant production run produces the parts and data for capability studies, measurement studies and the PPAP submission. The gate question is "Does the process we built behave like the process we planned?"

Phase 5: feedback, assessment and corrective action. Production has started. Variation is reduced, early problems are closed, and what was learned is written down for the next project. The gate question, usually asked at the end of the launch period, is "Is it stable, and can the project team hand it over?"

The phases overlap. Process design starts before product design finishes, and feedback runs throughout. The gates do not overlap. Each one is a date with a decision attached.

What the 3rd edition changed

The five phases are the same. What the 2024 edition added sits around them, and it shows where launches were failing.

  • Sourcing. A section and a checklist on choosing suppliers as part of the project, and an expectation that you review your sub-suppliers' planning as well as your own. Many launch failures start two tiers down.
  • Change management. A section and a checklist on handling changes during the project. A launch is a stream of changes, and each one can quietly undo a gate already passed. The method is in the engineering change management guide.
  • Risk assessment and mitigation. A plan that lists the project's risks and what is being done about each, kept current through the phases.
  • Programme metrics. Measures of the project's own health, which is also what IATF's monitoring requirement asks for.
  • Gated management. Guidance on running formal gates with defined expectations.
  • Part traceability. New content on how parts will be traced.
  • The control plan moved out. It now has its own manual, which added safe launch as a phase between pre-launch and production.

Read together, the changes say one thing: APQP is now treated as the way a project is governed, not as a way to produce quality documents.

The same launch in VDA words: maturity levels ML0 to ML7

German customers describe the same journey with a different method: Maturity Level Assurance for New Parts, published by the VDA, currently in its 3rd edition (2022). Instead of five phases it uses eight maturity levels, each a checkpoint tied to the customer's vehicle timeline.

  • ML0: innovation release, before series development starts.
  • ML1: the requirements for the contract are managed and understood.
  • ML2: the supply chain is defined and orders are placed.
  • ML3: technical specifications are released.
  • ML4: production planning is complete.
  • ML5: parts from series tools and series equipment are available.
  • ML6: product and process are approved. This is where the VDA's equivalent of PPAP, the production process and product approval (PPA), sits.
  • ML7: the project closes, responsibility passes to series production, and requalification starts.

Three things are worth knowing if you supply both worlds.

First, the mapping is close. ML1 and ML2 cover what APQP calls phase 1 plus sourcing. ML3 is the end of product design. ML4 is the end of process design. ML5 and ML6 are validation and approval. ML7 is the handover. If your gate system satisfies one method it is most of the way to satisfying the other.

Second, the VDA method sorts parts by risk, usually into classes A, B and C, and the class decides how closely the customer follows the part. High-risk parts are assessed jointly with the customer at each level. Low-risk parts are left to the supplier's own assessment. Ask early which class your part is in, because it sets the workload.

Third, each maturity level is assessed against measurement criteria and reported with a status, commonly red, amber or green. A red status is escalated and needs a recovery plan before the project moves on. That is the gate idea, stated more bluntly than APQP states it.

The VDA 6.3 process audit looks at the same project through its elements P2 (project management), P3 (planning) and P4 (carrying out the development). If a German customer audits your launch, those are the questions you will be asked.

What customers add on top

Every vehicle manufacturer layers its own system over these methods. Ford splits PPAP into phases that separate quality proof from capacity proof. GM adds its own project plan, run-at-rate and early production containment. Stellantis rates every deliverable on a grid at each gate. Volkswagen Group runs a qualification programme for new parts with a multi-day production trial. Renault and Nissan have their own five-phase procedure.

You do not need to memorise them. You need one habit: at kick-off, list which customer documents govern this project, get the current revision of each, and put the customer's milestones on the same timing plan as your own gates. Most launch surprises are a customer milestone nobody had on the plan.

Six ways launches fail at the gates

  • Gates passed on dates. The review happens because the calendar says so, and the open items become "actions". A gate with twelve open actions has not been passed.
  • Feasibility signed by one person. The commitment is made by sales or by the project lead alone, and manufacturing first sees the drawing after the award.
  • The PFMEA written after the tools arrive. By then it describes the process instead of shaping it, and its findings cost far more to act on.
  • Capacity proven on a good day. One shift with the best setter and no changeovers is not the quoted rate.
  • Sub-suppliers managed by purchase order. Their tooling, their capability and their approval are on your critical path. Put them on your timing plan.
  • No handover. The project team moves to the next launch, and production inherits a process whose open issues live in one engineer's notebook.

Start this week

Take one project that is running now and write its gates on one page: the date, the question, who decides, and what evidence they will see. Then mark the status of each piece of evidence honestly in red, amber or green. If the next gate is within a month and anything is red, that is the conversation to have today, while there is still time to move a date or add a resource.

Then look one tier down. For each bought-in part or outside process on the bill of materials, ask whether you have seen the supplier's timing plan and when their approval is due. If the answer is no, you have found the most likely cause of your next launch delay.

The free Launch Gate Checklist below sets out the five gates with the questions each one must answer, a one-page status summary and an open-issues list. It works for APQP phases and can be relabelled for VDA maturity levels.

Frequently asked questions

Is APQP mandatory? IATF 16949 requires planned, cross-functional, monitored product and process development. It does not name APQP. Your customer usually does, in its customer-specific requirements, and then it is mandatory for that customer.

What is the difference between APQP and PPAP? APQP is the project. PPAP is the evidence package produced near the end of it, in phase 4, to show the customer the project worked.

We build to print. Do phases 1 and 2 apply to us? Phase 1 applies in full. In phase 2 your job is the manufacturing feasibility review of the customer's design and your input on special characteristics. Skipping it is how suppliers end up holding a tolerance they never agreed they could hold.

How many gates should we have? One at the end of each phase is the minimum. Many companies add a gate before the tooling order and one before the first shipment, because those are the two points where the money and the risk jump.

Do we need both APQP and the VDA maturity levels? Only if you have customers from both families. Build one internal gate system and keep a mapping sheet that shows which of your gates answers which APQP phase and which maturity level.

What is safe launch? A period at the start of production with extra checks beyond the normal control plan, kept until agreed exit criteria are met. It is covered in the control plan guide.

Who should chair the gate review? Someone who can stop the project. If the chair cannot say no, the meeting is a status update.

Is anything about to change? Yes. The IATF has said that launch management, meaning new products, changes and industrialisation, is one of five priority topics for the next edition of IATF 16949, planned for mid-2027. No clause text has been published, but the direction is clear: more structure around launches, not less.

Get the free Launch Gate Checklist (five gates, the eight checks behind each one, a red/amber/green summary, an open-issues list and a map from APQP phases to VDA maturity levels)

Free, instant download. We'll only email you the occasional practical quality update — no spam, unsubscribe anytime.

Put this into practice

The PFMEA Toolkit is the analysis engine of the chain — the AIAG-VDA 7-step form as a working Excel workbook, with Action Priority calculated for you from the full S-O-D logic, a linked process flow tab, and the control plan handoff mapped out on the same worked example as the free templates. For the characteristics the PFMEA then sends to real statistical control, the SPC Control Chart Toolkit is X-bar/R, capability and the out-of-control rules in the same working style.

More in this series

Want to put this to work in your own system? The templates, toolkits and free masterclasses are built on the same guidance.

Browse templates

Certification & implementation

Working on a certification or system implementation project?

Implementing ISO 9001, moving to the 2026 edition, getting ready for a certification audit, or stuck on a clause that doesn't seem to fit your operation? Tell us where you are and where you're stuck. We'll look at it and suggest a practical next step, or connect you with people we trust who can help.

Email hello@qlause.app

No sales pitch, no obligation — we read every message.