Food & beverage · worked example
Value stream map example: a sauce bottling line
A shared cooking kettle works to a weekly plan, the filling line loses more than a fifth of its time to stoppages and flavour flushes, and six days of finished pallets cover for it. Run through the guide, the line gets supermarkets after cooking and filling, a labelling-and-packing cell that sets the pace, and SMED and TPM on the filler.
The current state
Table sauces, 750 ml glass (6 flavours): 96 000 bottles a month (customer: Retail distribution centre), on 2 shifts of 8 hours. That makes 4 800 bottles a day and a takt time of 11.3 seconds. Filling & capping is over takt once stoppages and rework are counted (Filling & capping: 11.7 s effective against 11.3 s).
- Lead time
- 18 days
- raw material to customer
- Processing time
- 32 s
- actually worked on
- Flow efficiency
- 0.003%
- processing ÷ lead time
- Schedule points
- 4
- places told what to make
What the improvement guide recommends
Run through the builder's nine future-state questions, accepting each recommendation, this value stream gets one pacemaker (Labelling + Case packing) and these 10 actions — each one a kaizen burst on the future-state map:
- 1Pull (kanban)Set up a kanban supermarket after Batch cooking (about 7 200 bottles); Batch cooking makes only what Filling & capping withdraws
- 2SMEDCut Filling & capping changeover from 40 to 20 min (SMED)
- 3TPMRaise Filling & capping uptime from 78% to 95% (TPM: find and fix the stoppages)
- 4Pull (kanban)Set up a kanban supermarket after Filling & capping (about 7 200 bottles); Filling & capping makes only what Labelling + Case packing withdraws
- 5Continuous flowBuild a continuous-flow cell: Labelling + Case packing (3 operators, one piece at a time)
- 6TPMRaise Labelling uptime from 88% to 95% (TPM: find and fix the stoppages)
- 7PacemakerSend the customer schedule to Labelling + Case packing only — every other process is triggered by kanban or FIFO
- 8HeijunkaLevel the mix and volume at Labelling + Case packing: release one pitch of work (12 bottles) at a time from a load-leveling box
- 9Pull (kanban)Hold finished goods in a supermarket of about 7 200 bottles (1.5 days) that shipping withdraws from
- 10Supplier pullAgree daily deliveries with Packaging and ingredient suppliers and refill a raw-material supermarket from kanban
The future state: 18 days down to 6 days
- Lead time
- 6 days
- from 18 days (−67%)
- Stock
- 28 800 bottles
- from 86 400 (−67%)
- Working capital freed
- R1.04 million
- at R18 a unit
- Schedule points
- 1
- from 4
More value stream map examples
- Metal fabrication: steel brackets — the builder's main worked example, 37.5 days to 8.
- Furniture & joinery: painted cabinet doors — MDF doors through CNC cutting, sanding, a shared paint booth, drilling and packing — with repaint rework and a drilling station over takt.
- Clothing & textiles: workwear shirts — Shirts through cutting, a 30-operator sewing line, buttons, pressing and packing — with three weeks of fabric at the front and a sewing line over takt.
New to the symbols? See the VSM symbols cheat sheet.